← Back to index
TransitConstruction Project2026–

Change management across a system-wide vertical transportation replacement program.

Value
$146M + $192M
Client
MTA Construction & Development
Role
Change Manager
Location
New York, NY
Change ManagementEntitlementIndependent EstimatesNegotiation

Program management consultancy for two MTA design-build contracts covering the replacement of 21 escalators at six subway stations and 37 elevators at 17 stations. Builders: Skanska and the Forte/Gramercy JV. Designer: Stantec.

Key contributions

  • Reviewed and corrected previously assessed scope, identified overlooked credits, and provided technical grounding for change-order presentations to the client's executive committees.
  • Audited previously negotiated change orders, identifying material-quantity discrepancies and unsubstantiated labor production rates.
  • Led scope-reconciliation meetings with the contractor — resulting in formal acknowledgment of the identified overstatements.
  • Prepared independent cost estimates for both construction and design across a high volume of changes on both contracts.