Program management consultancy for two MTA design-build contracts covering the replacement of 21 escalators at six subway stations and 37 elevators at 17 stations. Builders: Skanska and the Forte/Gramercy JV. Designer: Stantec.
Key contributions
- Reviewed and corrected previously assessed scope, identified overlooked credits, and provided technical grounding for change-order presentations to the client's executive committees.
- Audited previously negotiated change orders, identifying material-quantity discrepancies and unsubstantiated labor production rates.
- Led scope-reconciliation meetings with the contractor — resulting in formal acknowledgment of the identified overstatements.
- Prepared independent cost estimates for both construction and design across a high volume of changes on both contracts.